Q: Why does the progress not change on the status page? And why do some Contractors display the status “No involvement in any Work Packages?”

The status of the Contractor’s data, changes to “In Progress” when a Contractor starts editing. The status changes to “Finalised” when the Contractor clicks the Finalise button. If the status shows “No involvement in any WPs” in the Work Package description column, then the Contractor has not been involved by the planned staff effort in any Work Package or Task.