Under Proposal > Work Plan > Milestones or DoW > Work Plan > Milestones you are able to plan the milestones within your project.
To add a milestone, select a Work Package and click the button below the Work Package item. Specify the Name and Expected Month of the milestone as well as describe the Means of Verification and type in the Involved Work Packages. Please note one milestone can be involved in more than one Work Package.
Click the button to delete a milestone.
To move a milestone to another Work Package, click on the button on the right of the particular milestone. A dialog box will appear and you can select the new Work Package by confirming with