I cannot open a task, when reporting consumed person months. What can I do?
Oct 6, 2017 6444 Print this page Download PDF Request support
The system does not allow to record person-months on certain tasks when those tasks are not running along the selected reporting period.
In order to be able to record person-months on tasks, please assure that the tasks run throughout the selected reporting period. You can change the actual start and end of tasks at Implementation > Reporting > Progress > WPX > Task X.X by modifying the fields Actual Start & End accordingly in order to cover the selected reporting period.