March 5, 2013 FAQ's 2085
The reporting periods can always be changed along the project duration....
March 5, 2013 FAQ's 1945
You have the ability to export the Gantt Chart at any time through the Version/Export tab. The chart is under the Description of Work 8211; Part B section 8220;The timing of the different WPs and their components.8221; It is possible to export this section separately or together with the entire DoW....
March 5, 2013 FAQ's 1701
Exported reports can only provide information from within the selected report period. For example, if you selected to export an Interim Report covering the M01-M03 period, the report will only retrieve the information dated within that period. That means that if the status of a deliverable or milestone was reported outside this period, it will...
March 5, 2013 FAQ's 1749
At any time you can generate and export a report ,even if it is simply a draft, for any of the defined reporting periods under Version/Export. Please select the correct reporting period from the left side panel and click on one of the available exports in the main area....
August 4, 2015 FAQ's 7296
EMDESK offers a large number of options to export of your online project data into offline DOCX and XLS documents. You can perform an export at any time. EMDESK automatically generates Proposals, Reports, the Technical Annex, and Financial Statements that need to be provided during the Project Implementation Phase. To export a document click on Version...
March 5, 2013 FAQ's 2556
At any time reports and financial forms, depending on the defined reporting periods, can be generated on demand and downloaded to the desktop. EMDESK exports ready-for-submission Interim and Periodic Reports, Staff Effort and Budget Tables, Deliverable Statuses, Cost Statements and Financial Reports for further streamlining in all major word processing or calculation software such as...
March 5, 2013 FAQ's 2550
There are several things you can do. First, try to re-send the invitation. Go to myEMDESK > Project Settings > User Accounts and re-send the invitation by clicking on the button Re-invite at the user entry in the panel Not confirmed invitations. Second, ask the user whether they checked for the mail in the inbox...
March 5, 2013 FAQ's 1672
The administration of the Contractors is done under Proposal or DoW > Contractor > Contractors and also to deactivate a Contractor item. Please note the Contractor items cannot be deleted in order to keep the contracted partner numbering in line. Please note that you properly need to re-shuffle the Contractor8217;s budget and efforts of active...
March 5, 2013 FAQ's 4366
To modify the project plan duration, go to Proposal > Project > General Information and enter the new duration in months into the Duration input field. All Contractors participation periods will automatically be set to the new project duration, unless an individual participation period of a Contractor needs to be defined then tick the check...
March 5, 2013 FAQ's 1927
The Task Leader can only be set by the Project Coordinator through Proposal > Work Plan > WP Structure. As for partners being assigned to tasks, go via the claiming plan of person-months under Proposal > Work Plan > Resources....